Clark Science CenterRenovation Project PageThe Clark Science Center renovation project, which involves Sabin-Reed and Burton buildings, is scheduled to take place from spring 2010 through January 2012. Majority of project involves code upgrades (sprinkler system, HVAC, electrical, ADA compliance) which is followed by some programming renovations. Renovation Operations Committee (ROC) The Renovation Operations Committee (ROC) is responsible for general project management and decision-making. See the Renovation Operations Committee page which includes meeting minutes and other planning updates. Emergency Contact ListIf any construction related emergency occurs within Sabin Reed or Burton Hall, please use the following list to contact someone from the construction team :
General Construction Info
Sabin-Reed and Burton Hall : Equipment supplied on standby power Project Notifications This page is maintained by Chad Siebel on behalf of the Renovation Project Management Team. Most recent posts on the top.
December 19, 2011Electrical Shutdown: 6:00AM Tuesday, December 27th - 6:00PM Thursday, December 29th
As previously advised, the construction project associated within Sabin-Reed and Burton Hall requires an additional electrical shutdown during the week of Christmas Break. This shutdownt will affect Sabin-Reed, Burton Hall, McConnell Hall and Bass Hall.
PLEASE CLICK ON LINK BELOW FOR EQUIPMNET IN SABIN-REED AND BURTON HALL THAT IS SUPPLIED BY STANDBY POWER
Below you will find building specific information that will occur during the shutdown as well as ITS information: Phone Services All Office/lab phones within Bass, McConnell, Sabin-Reed and Burton Hall will not work during this shutdown. There will be 1 working phone within the corridor of the 1st floor of these buildings. These phones will be labeled prior to and during the shutdown in case of any type of emergency. Animal quarter’s phone will remain active during the shutdown.
July 4, 2011Room Construction: The contractors continue to work within program and non-program spaces throughout Sabin-Reed and Burton Hall. A revised "Room Turn Over" schedule has been updated based on the current status within each room - CLICK HERE FOR - 07-04-11 Room Turnover Schedule
Burton Hall Window Replacement: The contractors have completed all window replacement within exception to 3 basement windows which are anticipated to arrive on campus within the next few weeks. The architect has reviewed each window throughout Burton Hall and has issued back to the contractor the punchlist associated with the cosmetic trim work around the interior of the windows. It is estimated that all punchlist items will be complete by the end of July. Screens: Window screens will be installed after the scaffolding associated with the Burton Hall roof replacement has taken down.
Corridor Refinishing: The contractors have installed 90% of all drywall throughout Sabin-Reed and Burton Hall over existing wood paneling. All other drywall installation will occur during the scheduled August electrical shutdown. Painting of the new drywall has begun on the 4th & 3rd floors of Sabin-Reed and will continue through the floors over the next month.
May 6, 2011The following information was shared at the Town Hall Meeting held on Wednesday, May 4th: As the month of May makes its way to commencement activities, the construction team is gearing up for a long summer semester as there is a tremendous amount of work that will occur in and around Sabin-Reed and Burton Hall beginning May 23rd. These activities include but are not necessarily limited to:
Information regarding each of these activities has been summarized below for your information.
Burton Hall Window Replacement - CLICK HERE FOR - Burton Hall Window Replacement Schedule Beginning on Monday, May 23rd the contractor will begin to remove and replace all windows within Burton Hall. The schedule that has been developed and will need to be maintained requires that all windows on each floor are replaced prior to the start of work on other floors. This is due not only to the number of windows that are scheduled to be replaced, but also the fabrication and delivery of windows. As scheduled, the contractor will begin work on the 3rd floor and then move down to the lower floors, completing their work at the basement level. Please keep in mind that all dates are weather permitting. This work will affect each faculty member whose office, classroom or lab has a window(s) in Burton Hall as well as all classrooms. During the removal and replacement of the windows, access to offices, research labs, classrooms, etc. will not be granted and we will need to coordinate with each faculty member about the contents of rooms which will need to be moved (similar to the coordination that was followed during sprinkler installation) to allow the contractors free and unrestricted access to the windows. The process of identifying what items will need to be moved will begin the week of May 9th.
Sabin-Reed and Burton Hall Roof Replacement The roofing at Sabin-Reed and Burton Hall is scheduled to begin the 2nd week in June. Preparations for the roofing replacement will begin immediately as there are multiple existing Sabin-Reed roof curbs which will need to be removed as well as piping and conduit stands that are being replaced / installed for the new emergency generator. These activities will be discussed with the current occupants on the 4th floor of Sabin-Reed beginning the week of May 9th. The roofing replacement of Burton Hall requires that the contractor set up scaffolding around the entire facade of Burton Hall. This work will begin on May 23rd and it is expected that the scaffolding will remain in place throughout the summer semester. The North and South exit doors of Burton Hall will continue to be used as exit only doors, however keep in mind that due to the Burton Hall Dome Restoration project, the entry into Burton Hall will be shutdown starting May 23rd.
Burton Hall Dome Restoration - Entry Shutdown beginning Monday, May 23rd The existing Burton Hall entrance dome circa 1906 will be restored beginning on May 23rd. This work involves relocating the existing interior storefront door system further into the 1st floor hallway and will provide a new double door into and out of the entrance vestibule. Due to the work involved, the entry to Burton Hall will be shutdown beginning Monday, May 23rd through the summer semester. It is anticipated that the Burton Hall entry will be reopened Tuesday, September 6th. During this timeframe, please use the Sabin-Reed entrance as a means to gain access into Burton Hall.
IT Infrastructure Upgrade of Sabin-Reed and Burton Hall The existing data and telephone system wiring will be replaced entirely throughout Sabin-Reed and Burton Hall over the course of the summer semester. This will affect all spaces within the buildings as the old wires that support computers, telephones, printers, etc. will need to be removed and replaced with newer and improved cables which will be tied back to the new data closets that have been constructed within the buildings over the course of the past year and a half. During the time that the old wires are removed and new wires installed & tied back / terminated and tested to the new data closet equipment, IT will not work within occupied spaces. It is anticipated that this work will require 3-4 days within occupied spaces and during this timeframe there will be no IT support within the space. The Data/IT contractor is currently formulating a schedule within both buildings and how it will affect each occupied space. As we obtain more information from the contractor we will provide more information.
Sabin-Reed and Burton Hall Corridor Refinishing - All items on all corridor walls throughout Sabin-Reed and Burton Hall must be removed no later than Friday, June 3rd The project will be moving forward with the drywall installation over all existing wood paneling throughout Sabin-Reed and Burton Hall. This work is scheduled to begin on Monday, June 13th. Work involved includes:
As the contractors will need to remove all existing tackboards throughout the buildings, faculty will be required to remove all posters, notices, bulletins, etc. no later than Friday June 3rd. Any items remaining after June 3rd on the tackboards or wall surfaces will be removed and disposed of.
Program Space Construction and Turnover to Faculty CLICK HERE FOR - Program Space Construction and Moving Schedule CLICK HERE FOR - Program Space Hand Off Procedures CLICK HERE FOR - Moving Out Procedures
As the project moves forward with turning over program spaces, we have developed specific procedures on how program spaces will be turned over to faculty. Prior to the completion date of program space construction, the contractor will advise that work is at substantial completion and the space should have a punchlist developed by the end user of the space. Once this information has been advised by the contractor the faculty member who has been listed as the end user of the space will be contacted to walk the space with the Smith Project Manager to develop a punchlist specific to items that might not have been completed per the construction documents. This walkthrough must be conducted no later than one week after the contractor notifies "substantial completion of the space". Please reference the "Program Space Hand Off Procedures" link above for further information as the space pertains to key requests, AV Equipment, Furniture, and Moving. Please reference back to the "Program Space Construction and Moving Schedule" matrix link above and understand when construction program space or vacant spaces will be turned over to faculty members over the course of the summer semester. MOVING In order for the contractor to properly take possession of currently "occupied" spaces that are scheduled as program construction space or will be turned over to a different faculty member, faculty will be required to ensure that at the end of the day of a scheduled move out and/or move in, that their existing rooms are free and clear of all contents, chemicals, glassware, paperwork, etc. All material that is left behind will be removed and disposed of. Please reference the "Moving Out Procedures" link above for more information as it pertains to packing of material throughout an occupied space. As indicated, the following rooms will need to be moved out / into over the course of the month of May: SR-101C : May 9th Move Out SR-229 : May 23rd Move In SR-230 : May 23rd Move In SR-235 : May 23rd Move Out SR-236 : May 23rd Move Out SR-302 : May 23rd Move Out SR-303 : May 23rd Move Out SR-304 : May 23rd Move Out SR-305 : May 23rd Move Out SR-338 : May 23rd Move In SR-339 : May 23rd Move In SR-340 : May 23rd Move In SR-351: May 23rd Move Out SR-352 : May 23rd Move Out SR-406 : May 23rd Move In SR-407 : May 23rd Move In SR-454: May 23rd Move In SR-455: May 23rd Move In Electrical Shutdown: 5:00PM Friday, August 4th - 12:00PM Sunday, August 14th The construction project associated within Sabin-Reed and Burton Hall includes the removal and replacement of the emergency generator and power transfer switch. This work and subsequent associated electrical work related to the emergency generator and transfer switch replacement will require a power shutdown which will affect Sabin-Reed, Burton Hall, McConnell Hall and Bass Hall. The contractors will begin to shut power off to these buildings beginning at 5:00PM on Friday, August 5th and will have full power restored by 12:00PM on Sunday, August 14th. During this timeframe, only life safety devices (emergency lighting) and standby power for essential equipment will have continuous power supplied to them. All other electrical systems and convenience outlets that serve such items as office lights, computers, AV devices, copiers, printers, etc. WILL NOT have power supplied to them within Sabin-Reed, Burton Hall, McConnell Hall and Bass Hall. Please reference the links below for equipment that will have continuous power supplied to them throughout the power shutdown and also more information of how this shutdown will affect faculty, staff and students.
CLICK HERE FOR - Critical Equipment During Shutdown CLICK HERE FOR - Electrical Shutdown Information
December 20, 2010There is an extensive amount of work that will occur within Burton Hall over the next month. The primary goal is to complete all work within the 1st floor Corridor Work of Burton Hall no later than the start of Spring Semester Classes. Other work throughout Burton Hall is noted below:
Burton Hall Basement Corridor Flooring - Floor Shutdown The contractor will begin the removal of the corridor flooring which involves taking control of basement level of Burton Hall and also the basement level of the Central Stair connecting Sabin-Reed to Burton Hall. Please note that no access will be allowed during the following timeframes
Burton Hall Basement
Burton Hall 1st Floor
Burton Hall 3rd Floor
NO ACCESS WITHIN THE FOLLOWING ROOMS Non Accessible Rooms Work has been scheduled in the following occupied rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted:
Upcoming Electrical Panel Changes & Associated Power Loss Friday December 24th
Monday December 27th
Tuesday December 28th
Wednesday December 29th -
Thursday December 30th
November 2, 2010 - Info on renovation paint and carpetMSDS sheets: October 22, 2010 - Detailed Drawings for Sign-off IMPORTANT DATES TO REMEMBER October 15, 2010Please note that starting Monday October 25th, the contractor will begin working on the 2nd Floor of Burton Hall. October 12, 2010Please note that during the October 20th construction update presentation being held in McConnell Hall, I will be distributing the most current programming documents for each space to the room occupant users. The design team will be on campus starting Wednesday October 27th at 8:30AM through the end of the day on Friday October 30th to review these drawings with each user and obtain final approval (sign-off). There will be another email following to set up a meeting with the designers. I will be available in the Schalk Lounge within Sabin-Reed on Friday October 22, Monday October 25 and Tuesday October 26 between the hours of 1-3PM to provide assistance reviewing the drawings. We want to make everyone aware that this is the single most important juncture on this project. The review of these drawings and the ability to provide any comments or questions during the sign-off meetings with the designers will then provide the design team to incorporate them into a permit set, which will then be submitted to the City of Northampton for permitting, followed by construction. This will be the last opportunity to make changes within the rooms. IMPORTANT DATES TO REMEMBER
October 1, 2010 Burton Hall North Stair
Burton 3rd Floor
Non Accessible Rooms Work has been scheduled in the following occupied rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted:
ROOM BY ROOM SCHEDULE (Dated 10/1/10) - All Floors of Burton Hall
1 MONTH LOOK AHEAD SCHEDULE (Dated 10/1/10)
September 10, 2010Burton Hall North Stair
Burton Hall 4th Floor
Burton 3rd Floor
Burton 2nd Floor
Burton 1st Floor
ROOM BY ROOM SCHEDULE (Dated 9/10/10) - All Floors of Burton Hall Below you will find a Room by Room Schedule for all floors of Burton Hall.
1 MONTH LOOK AHEAD SCHEDULE (Dated 9/10/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
August 30, 2010Sabin-Reed
Burton Hall Entrance
Burton Hall
August 6, 2010!!!!NEXT SATURDAY!!!! - Electrical Shutdown - Sabin-Reed, Burton Hall, McConnell Hall & Bass Hall - Saturday August 14 2:00AM - 6:00AM The electrical service servicing Sabin-Reed, Burton, Bass and McConnell Hall will need to be shutdown for approximately 4 hours and we have advised the project team to schedule this shutdown for: Saturday August 14th between the hours of 2:00AM - 6:00AM. During this shutdown, the existing emergency generator within Sabin-Reed will activate, providing power back to all life safety devices within each building as well as any pieces of equipment that are currently tied into the emergency power system. Other than life-safety, we have confirmed that the following equipment will have powered supplied to them by the emergency generator:
Please put any refrigerated items in one of these locations or in Ford Hall. If you have other pieces of critical equipment that could not sustain a 4 hour power loss, please identify these pieces of equipment and room number no later than August 1st. As well as power shutdown during this timeframe, the data center within Bass Hall, which ties all of the Science Center buildings into the Smith network, will also be shutdown. Burton Hall Corridor Flooring and Ceiling Removal - Floor Shutdowns The contractor will begin the removal of the corridor ceiling and flooring which involves taking control of one stairwell and two floors simultaneously over two separate weekends in August to accelerate this portion of work of the project. Please note the following schedule for each floor and stairwells within Burton Hall:
During these timeframes, access to rooms on the floors indicated will not be allowed as the floors will be shut down to all faculty, staff and students. You will need to ensure that you are off of these floors no later than 5:00PM on the Friday indicated so that the contractor can take control of the floors and begin the prep work to remove the floors and ceilings. Access to the floors will be granted at 7:00AM the following Monday morning Construction Update
ROOM BY ROOM SCHEDULE (Dated 8/6/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 8/6/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
July 30, 2010 !!!!2 Weeks Away!!!! Electrical Shutdown - Sabin-Reed, Burton Hall, McConnell Hall & Bass Hall - Saturday August 14 2:00AM - 6:00AM The electrical service servicing Sabin-Reed, Burton, Bass and McConnell Hall will need to be shutdown for approximately 4 hours and we have advised the project team to schedule this shutdown for: Saturday August 14th between the hours of 2:00AM - 6:00AM. During this shutdown, the existing emergency generator within Sabin-Reed will activate, providing power back to all life safety devices within each building as well as any pieces of equipment that are currently tied into the emergency power system. Other than life-safety, we have confirmed that the following equipment will have powered supplied to them by the emergency generator: Please put any refrigerated items in one of these locations or in Ford Hall. If you have other pieces of critical equipment that could not sustain a 4 hour power loss, please identify these pieces of equipment and room number no later than August 1st. As well as power shutdown during this timeframe, the data center within Bass Hall, which ties all of the Science Center buildings into the Smith network, will also be shutdown. Burton Hall Corridor Flooring and Ceiling Removal - Floor Shutdowns The contractor will begin the removal of the corridor ceiling and flooring which involves taking control of one stairwell and two floors simultaneously over two separate weekends in August to accelerate this portion of work of the project. Please note the following schedule for each floor and stairwells within Burton Hall: * North Stair, 4th and 3rd Floors : Friday August 13th 5:00PM Monday August 16th 6:00AM * South Stair, 2nd and 1st Floors : Friday August 20th 5:00PM Monday August 23rd 6:00AM During these timeframes, access to rooms on the floors indicated will not be allowed as the floors will be shut down to all faculty, staff and students. You will need to ensure that you are off of these floors no later than 5:00PM on the Friday indicated so that the contractor can take control of the floors and begin the prep work to remove the floors and ceilings. Access to the floors will be granted at 7:00AM the following Monday morning.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 7/30/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 7/30/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
July 23, 2010 Electrical Shutdown - Sabin-Reed, Burton Hall, McConnell Hall & Bass Hall - Saturday August 14 2:00AM - 6:00AM The electrical service servicing Sabin-Reed, Burton, Bass and McConnell Hall will need to be shutdown for approximately 4 hours and we have advised the project team to schedule this shutdown for: Saturday August 14th between the hours of 2:00AM - 6:00AM. During this shutdown, the existing emergency generator within Sabin-Reed will activate, providing power back to all life safety devices within each building as well as any pieces of equipment that are currently tied into the emergency power system. Other than life-safety, we have confirmed that the following equipment will have powered supplied to them by the emergency generator: Please put any refrigerated items in one of these locations or in Ford Hall. If you have other pieces of critical equipment that could not sustain a 4 hour power loss, please identify these pieces of equipment and room number no later than August 1st. As well as power shutdown during this timeframe, the data center within Bass Hall, which ties all of the Science Center buildings into the Smith network, will also be shutdown. Burton Hall Corridor Flooring and Ceiling Removal - Floor Shutdowns The contractor will begin the removal of the corridor ceiling and flooring which involves taking control of one stairwell and two floors simultaneously over two separate weekends in August to accelerate this portion of work of the project. Please note the following schedule for each floor and stairwells within Burton Hall: * North Stair, 4th and 3rd Floors : Friday August 13th 5:00PM Monday August 16th 6:00AM * South Stair, 2nd and 1st Floors : Friday August 20th 5:00PM Monday August 23rd 6:00AM During these timeframes, access to rooms on the floors indicated will not be allowed as the floors will be shut down to all faculty, staff and students. You will need to ensure that you are off of these floors no later than 5:00PM on the Friday indicated so that the contractor can take control of the floors and begin the prep work to remove the floors and ceilings. Access to the floors will be granted at 7:00AM the following Monday morning.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 7/23/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 7/23/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
July 9, 2010 Sabin-Reed & Burton Hall Shutdown Sabin-Reed and Burton Hall will be closed beginning at 5:00PM Friday, July 16th, and extending through Tuesday night, July 20th to complete the fire alarm panel upgrade of both buildings. During this timeframe, access to the building will not be granted. It is anticipated that access to the building will be granted at 7:00AM on Wednesday July 21st. Burton Hall Corridor Flooring and Ceiling Removal - Floor Shutdowns The contractor will begin the removal of the corridor ceiling and flooring which involves taking control of one stairwell and two floors simultaneously over two separate weekends in August to accelerate this portion of work of the project. Please note the following schedule for each floor and stairwells within Burton Hall: * North Stair, 4th and 3rd Floors : Friday August 13th 5:00PM Monday August 16th 6:00AM * South Stair, 2nd and 1st Floors : Friday August 20th 5:00PM Monday August 23rd 6:00AM During these timeframes, access to rooms on the floors indicated will not be allowed as the floors will be shut down to all faculty, staff and students. You will need to ensure that you are off of these floors no later than 5:00PM on the Friday indicated so that the contractor can take control of the floors and begin the prep work to remove the floors and ceilings. Access to the floors will be granted at 7:00AM the following Monday morning.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 7/9/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 7/9/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
July 2, 2010 Sabin-Reed & Burton Hall Shutdown Sabin-Reed and Burton Hall will be closed beginning at 5:00PM Friday, July 16th, and extending through Tuesday night, July 20th to complete the fire alarm panel upgrade of both buildings. During this timeframe, access to the building will not be granted. It is anticipated that access to the building will be granted at 7:00AM on Wednesday July 21st. Sabin-Reed South Stair Shutdown The south stair of Sabin-Reed will be shutdown beginning 7:00AM July 6th to install the handrail extensions as well as painting and installing new flooring. Access will not be allowed within the south stairwell until all items have been completed. Please use the central stairwell to access upper floors of Sabin-Reed.
Burton Hall Corridor Flooring and Ceiling Removal - Floor Shutdowns The contractor will begin the removal of the corridor ceiling and flooring which involves taking control of one stairwell and two floors simultaneously over two separate weekends in August to accelerate this portion of work of the project. Please note the following schedule for each floor and stairwells within Burton Hall: * North Stair, 4th and 3rd Floors : Friday August 13th 5:00PM Monday August 16th 6:00AM * South Stair, 2nd and 1st Floors : Friday August 20th 5:00PM Monday August 23rd 6:00AM During these timeframes, access to rooms on the floors indicated will not be allowed as the floors will be shut down to all faculty, staff and students. You will need to ensure that you are off of these floors no later than 5:00PM on the Friday indicated so that the contractor can take control of the floors and begin the prep work to remove the floors and ceilings. Access to the floors will be granted at 7:00AM the following Monday morning.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 7/2/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 7/2/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
June 24, 2010 Sabin-Reed & Burton Hall Shutdown Sabin-Reed and Burton Hall will be closed beginning at 5:00PM Friday, July 16th, and extending through Tuesday night, July 20th to complete the fire alarm panel upgrade of both buildings. During this timeframe, access to the building will not be granted. It is anticipated that access to the building will be granted at 7:00AM on Wednesday July 21st.
North Elevator Shutdown The North Elevator has been shutdown to complete shaft work and finish upgrades within the cabs and is expected to be completed within 6-8 weeks. Sabin-Reed South Stair Shutdown The south stair of Sabin-Reed will be shutdown beginning the second week in July to install the handrail extensions as well as painting and installing new flooring. Access will not be allowed within the south stairwell until all items have been completed. Please use the central stairwell to access upper floors of Sabin-Reed. Construction Update:
Non Accessible Rooms Work has been scheduled in the following occupied rooms during the following dates. Access to these rooms will not be allowed during the timeframes not
June 10, 2010 1st Floor Shutdown - Friday June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Sabin-Reed & Burton Hall Shutdown Sabin-Reed and Burton Hall will be closed beginning at 5:00PM Friday, July 16th, and extending through Tuesday night, July 20th to complete the fire alarm panel upgrade of both buildings. During this timeframe, access to the building will not be granted. It is anticipated that access to the building will be granted at 7:00AM on Wednesday July 21st.
North Elevator Shutdown The North Elevator will be shutdown beginning June 21st to complete shaft work and finish upgrades within the cabs.
Construction Update:
Non Accessible Rooms Work has been scheduled in the following occupied rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted.
ROOM BY ROOM SCHEDULE (Dated 6/10/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 6/10/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
June 4, 2010 2nd Floor Shutdown - TONIGHT beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 7th. 1st Floor Shutdown - June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Construction Update:
Non Accessible Rooms Work has been scheduled in the following occupied rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted.
ROOM BY ROOM SCHEDULE (Dated 6/4/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 6/4/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
May 28, 2010 2nd Floor Shutdown - June 4th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 7th. 1st Floor Shutdown - June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 5/28/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 5/28/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
May 21, 2010 2nd Floor Shutdown - June 4th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 7th. 1st Floor Shutdown - June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Construction Update:
ROOM BY ROOM SCHEDULE (Dated 5/21/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 5/21/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces.
May 14, 2010 2nd Floor Shutdown - June 4th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 7th. 1st Floor Shutdown - June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Construction Update:
Non Accessible Rooms Work has been scheduled in the following rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted.
ROOM BY ROOM SCHEDULE (Dated 5/14/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 5/14/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for specifics within your spaces. May 7, 2010 PLEASE NOTE: After commencement, the contractors will begin working on the 2nd and 1st floors 2nd Floor Shutdown - June 4th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 7th. 1st Floor Shutdown - June 11th beginning at 5:00PM. Floor will be reopened to faculty, students and staff at 7:00AM Monday June 14th.
Non Accessible Rooms Work has been scheduled in the following rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted.
ROOM BY ROOM SCHEDULE (Dated 5/7/10) - All Floors of Sabin-Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 5/7/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends. NOTE: Room by Room Schedule now includes all rooms on the basement, 1st and 2nd floors April 30, 2010 PLEASE NOTE: After commencement, the contractors will begin working on the 2nd and 1st floors and you will begin to see temporary construction barriers begin to be erected near the north side of the building corridor. They will begin all construction related activities in the vacant rooms on the North Side of the building and we are beginning to schedule the abatement of the tile flooring throughout the corridors of the 1st and 2nd floors.
Non Accessible Rooms Work has been scheduled in the following rooms during the following dates. Access to these rooms will not be allowed during the timeframes noted.
ROOM BY ROOM SCHEDULE (Dated 4/30/10) - 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for all floors of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 4/30/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
April 16, 2010 While most of the construction activities within Sabin Reed have been in locations where faculty members and students cannot see, the contractor is making good progress on the installation of the sprinkler system in vacant rooms of the 4th and 3rd Floors. Coring activities are ongoing within both stairwells and the standpipe in the North Stair is approximately 70% complete. The contractor continues to work on the fire alarm system throughout the building as well as continuing to install electrical and data conduits to the new electrical / data closet locations. There have been numerous conversations and coordination efforts by both the construction team and faculty members for the start of construction within occupied rooms on the 4th and 3rd Floors to allow most of the heavy construction (Wall coring, sprinkler hangers installed in ceilings, sprinkler mains and branch lines and fire alarm conduit installation). Access into occupied rooms will continue to be coordinated as the spring semester ends and summer semester begins to complete the remaining work on the 3rd and 4th floors (Fire alarm device installation and termination as well as any ceiling tile installation). NON ACCESSIBLE 4th FLOOR ROOMS DURING WEEKEND OF APRIL 17th: Sabin Reed 410, 411, 412, 413, 415 & 416 As discussed with each faculty member occupying spaces on the 4th floor of Sabin Reed, coring activities, sprinkler line installation and any fire alarm device installation have been scheduled for construction beginning today at 7:00AM and will last through Saturday 4/17/10 Night. The spaces will be turned back over to each faculty member by 7:00AM Sunday Morning 4/18/10. NON ACCESSIBLE 4th FLOOR ROOMS DURING WEEKEND OF APRIL 17th: Sabin Reed 449, 450 & 453 As discussed with the faculty member occupying the above referenced rooms on the 4th floor of Sabin Reed, coring activities, sprinkler line installation and any fire alarm device installation have been scheduled for construction beginning today at 7:00AM and will last through Sunday 4/18/10 Night. The spaces will be turned back over to each faculty member by 7:00AM Monday Morning 4/19/10. SPRINKLER INSTALLATION- OCCUPIED SPACES OF SABIN REED 3rd FLOOR TO BEGIN APRIL 30th - NON ACCESSIBLE ROOMS As discussed with each faculty member in Rooms 301, 302, 303, 304, 304A, 304B, 304C, 305, 306, 307 & 308, the construction team will take possession of these rooms beginning Friday April 30th at 7:00AM to complete all wall coring, sprinkler line installation and all conduit installation for the fire alarm system. These spaces will be turned back over at 7:00AM on Monday May 3rd. Taking control of these rooms for this amount of time will allow all heavy construction activities to occur and the only other construction that will need to occur should be the fire alarm wire pulling through the conduits and device installation and termination. Please make sure that you plan your schedules accordingly. SPRINKLER INSTALLATION- OCCUPIED SPACES OF SABIN REED 3rd FLOOR TO BEGIN MAY 7th- NON ACCESSIBLE ROOMS As discussed with the faculty member in Rooms 351 & 352, the construction team will take possession of these rooms beginning Friday May 7th at 7:00AM to complete all ceiling demolition, wall coring, sprinkler line installation and all conduit installation for the fire alarm system. These spaces will be turned back over at 7:00AM on Monday May 10th. Taking control of these rooms for this amount of time will allow all heavy construction activities to occur and the only other construction that will need to occur should be the fire alarm wire pulling through the conduits and device installation and termination as well as any ceiling tile installation. Please make sure that you plan your schedules accordingly. SPRINKLER INSTALLATION- OCCUPIED SPACES OF SABIN REED 3rd FLOOR TO BEGIN MAY 8th- NON ACCESSIBLE ROOMS As discussed with the faculty member in Rooms 346, 347, 348 & 349, the construction team will take possession of these rooms beginning Friday May 7th at 5:00PM to complete all wall coring, sprinkler line installation and all conduit installation for the fire alarm system. These spaces will be turned back over at 7:00AM on Monday May 10th. Taking control of these rooms for this amount of time will allow all heavy construction activities to occur and the only other construction that will need to occur should be the fire alarm wire pulling through the conduits and device installation and termination as well as any ceiling tile installation. Please make sure that you plan your schedules accordingly. ROOM BY ROOM SCHEDULE (Dated 4/16/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. PLEASE NOTE: The schedule has been updated to include some rooms for the Basement, 1st and 2nd Floor
1 MONTH LOOK AHEAD SCHEDULE (Dated 4/16/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
April 9, 2010 Coring activities have begun within both stairwells as well as vacant rooms of the 4th floor to allow for the installation of the sprinkler system. The standpipe within the 4th floor is approximately 45% installed and the sprinkler main installation has begun within the vacant rooms on the 4th floor of Sabin Reed. The contractor continues to work on the fire alarm system throughout the building as well as continuing to install electrical and data conduits to the new electrical / data closet locations. As a reminder the following rooms WILL NOT have access to them over this weekend beginning tonight at 5:00PM Friday, April 9th through Monday Morning 8:00AM April 12th:Sabin Reed Rooms 346, 347, 348, 349, 350 SPRINKLER INSTALLATION - SABIN REED 4th FLOOR As discussed with each faculty member occupying spaces on the 4th floor of Sabin Reed, coring activities for the sprinkler line installation have been scheduled for Friday April 16th for the following rooms: SR410, 411, 412, 413, 413, 415 & 416 SPRINKLER INSTALLATION & CEILING REMOVAL- SABIN REED 3rd FLOOR Looking ahead at the schedule, the contractor will begin coring activities within each space on the 3rd Floor to allow for the installation of the new sprinkler system. Within the next 1-2 weeks we will be issuing highlighted plans to each occupied space noting the locations of where the sprinkler line will make its way into each room. Again, the highlighted plan will indicated the walls of which any material / equipment or storage item that will need to be moved within 4 weeks of the scheduled coring activity. We will provide a deadline of when any items will need to be move in order to complete the coring activities while maintaining the schedule for this phase of the project. ROOM BY ROOM SCHEDULE (Dated 4/9/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 4/9/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends. March 31, 2010: The contractor is continuing to work on the fire alarm system throughout the building as well as begin preparations to install the sprinkler system within the 4th and 3rd floor. Coring activities within the North Stair have begun to allow for the installation of the sprinkler standpipe riser, which makes up one of the main points of connection for the sprinkler system on each floor. They are also beginning to layout for the ADA compliant bathrooms and new electrical and data closets. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF APRIL 10th As indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (SR346, 347, 348, 349, 350) will not be accessible during the weekend of April 10th as the remaining section of abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, April 9th through Monday Morning 8:00AM (Start of Classes) April 12th. Please make sure that you plan your schedules accordingly. SPRINKLER INSTALLATION - SABIN REED 4th FLOOR As discussed with each faculty member occupying spaces on the 4th floor of Sabin Reed, coring activities for the sprinkler line installation will begin the week of April 12th. The following rooms have been identified and discussed to have the coring performed on 4/16/09 - 4/17/09: SR410, 411, 412, 413, 413, 415 & 416. SPRINKLER INSTALLATION& REMOVAL OF CEILINGS- SABIN REED 3rd FLOOR Looking ahead at the schedule, the contractor will begin coring activities within each space on the 3rd Floor to allow for the installation of the new sprinkler system. Within the next 1-2 weeks we will be issuing highlighted plans to each occupied space noting the locations of where the sprinkler line will make its way into each room. Again, the highlighted plan will indicated the walls of which any material / equipment or storage item that will need to be moved within 4 weeks of the scheduled coring activity. We will provide a deadline of when any items will need to be move in order to complete the coring activities while maintaining the schedule for this phase of the project.
ROOM BY ROOM SCHEDULE (Dated 3/31/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 3/31/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
March 26, 2010: Approximately 90% of all hallway flooring abatement has been completed on the 3rd floor and the remainder of hallway flooring abatement is scheduled to be completed the weekend of April 10th. There will be some additional flooring abatement that will occur within 4th and 3rd floor vacant rooms to allow for the installation of new ADA compliant bathrooms as well as new electrical and data closets. Once we have approximate dates from the contractor for this work we will advise. Ceiling demolition within the hallways on the 4th floor has been completed and the ceilings on the 3rd floor hallway is approximately 90% removed. This is now allowing the engineers and contractors to review the space and make necessary changes to the layout of the sprinkler system piping, conduits and any new plumbing systems that will occur during the I/C/DM phase of this project. SPRINKLER INSTALLATION & REMOVAL OF CEILINGS- SABIN REED 4th FLOOR The contractor has provided the wall locations of the 4th Floor of Sabin Reed where the sprinkler pipe will pass through each space to allow for the installation of the sprinkler system. These plans and coring locations have been discussed with all occupied faculty members. The contractor has scheduled to begin all coring activities within these 4th Floors starting the week of April 12th. An e-mail will be sent out to each individual noting the exact date of when coring activities will occur within each space early next week.
ROOM BY ROOM SCHEDULE (Dated 3/26/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 3/26/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends. March 19, 2010: Abatement on the 3rd Floor is scheduled to be completed by the start of classes on Monday 3/22/10 at 8:00AM. As a reminder the following rooms WILL NOT have access to them over this weekend beginning tonight at 5:00PM Friday, March 19th through Monday Morning 8:00AM March 22nd: 300, 300A, 301, 302, 303, 303A, 304, 304A, 304B, 304C,305, 308, 342, 343, 344, 345, 346, 347, 348, 349, 350, 351 and 352. SPRINKLER INSTALLATION& REMOVAL OF CEILINGS- SABIN REED 4th FLOOR The contractor has provided the wall locations of the 4th Floor of Sabin Reed where the sprinkler pipe will pass through each space to allow for the installation of the sprinkler system. On Tuesday March 23rd, a floor plan indicating (highlighting) the wall in which any material / equipment or storage on this specific wall will need moved/relocated within 4 weeks of the scheduled coring activity will be left within each rooms doors. These plans will also be left in each department chairs mailboxes for distribution to the appropriate faculty member. Please reference the Room by Room Schedule for the approximate coring date. During next week, I would like to meet with each 4th Floor faculty members whose rooms are affected by this coring activity to ensure that the material / equipment or storage on the specified wall will be able to be relocated prior to the scheduled coring activity. SPRINKLER INSTALLATION& REMOVAL OF CEILINGS- SABIN REED 3rd FLOOR Looking ahead at the schedule to the middle of April, the contractor will begin coring activities within each space on the 3rd Floor to allow for the installation of the new sprinkler system. Within the next 2-3 weeks we will be issuing highlighted plans to each occupied space noting the locations of where the sprinkler line will make its way into each room. Again, the highlighted plan will indicated the walls of which any material / equipment or storage item that will need to be moved within 4 weeks of the scheduled coring activity. We will provide a deadline of when any items will need to be move in order to complete the coring activities while maintaining the schedule for this phase of the project. ROOM BY ROOM SCHEDULE (Dated 3/19/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 3/19/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
March 12, 2010: Abatement on the 4th floor has been completed and the contractor will be concentrating on completing the remainder of abatement on the 3rd Floor over the next 2 weekends. This weekends activities will consist of abating the flooring along the hallways adjacent to rooms 300, 300B, 306, 307, 308, 309,310, 311, 312, 314, 338, 339, 340, 341,342, 342A & 342B. Beginning tonight at 5:00PM, access to these rooms will not be allowed until Monday March 15th Morning at 8:00AM. As a reminder the following rooms WILL NOT have access to them over this weekend beginning tonight at 5:00PM Friday, March 12th through Monday Morning 8:00AM March 15th :300, 300B, 306, 307, 308, 309,310, 311, 312, 314, 338, 339, 340, 341,342, 342A & 342B NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 20th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 300A, 301, 302, 303, 303A, 304, 304A, 304B, 304C,305, 308, 342, 343, 344, 345, 346, 347, 348, 349, 350, 351 and 352) will not be accessible during the weekend of March 20th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 19th through Monday Morning 8:00AM (Start of Classes) March 22nd. Please make sure that you plan your schedules accordingly.
SPRINKLER INSTALLATION& REMOVAL OF CEILINGS Looking ahead at the schedule to the end of March, the contractor will begin coring activities within each space on the 4th & 3rd Floor to allow for the installation of the new sprinkler system. Beginning next week, the contractor and a facilities representative will walk each occupied space to review the area where the sprinkler line installation will makes its way into each room. During this walkthrough, each faculty member will be advised on any material / equipment or storage item that will need to be moved within 4 weeks of the scheduled coring activity. We will provide a deadline of when any items will need to be move in order to complete the coring activities while maintaining the schedule for this phase of the project.
BURTON HALL ENTRANCE Starting Friday at 5:00PM, March 12, the Burton Hall Entrance will be closed through the end of Summer for the construction of the new wheelchair lift and ADA Accessibility.
ROOM BY ROOM SCHEDULE (Dated 3/12/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 3/12/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
March 5, 2010: The abatement work on the 4th floor will be completed this weekend. This completion of work will generate more work on these floors as they relate more to the addition of Handicap Accessible bathrooms, sprinkler piping installation and all other mechanical system upgrades associated with this project. As a reminder the following rooms WILL NOT have access to them over this weekend beginning tonight at 5:00PM Friday, March 5th through Monday Morning 8:00AM (Start of Classes) March 8th :401, 402, 402A, 403, 404, 405, 406, 406A, 406B, 449, 450, 451, 452, 453, 454, 455, 455A, 456 & 457. ABATEMENT OF CORRIDOR FLOORS The contractor and abatement contractor now have an good understanding of the amount of manpower that will be required to remove the remaining floor within the hallway of the 4th and 3rd floor. This understanding of manpower has been captured into the room by room schedule and as indicated, all remaining flooring removal on the 4th and 3rd floor will only take one weekend within the areas indicated on the schedule, rather than the 2 weekends. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 300B, 306, 307, 308, 309,310, 311, 312, 314, 338, 339, 340, 341,342, 342A, 342B) will not be accessible during the weekend of March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 12th through Monday Morning 8:00AM (Start of Classes) March 15th. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 20th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 300A, 301, 302, 303, 303A, 304, 304A, 304B, 304C,305, 308, 342, 343, 344, 345, 346, 347, 348, 349, 350, 351 and 352) will not be accessible during the weekend of March 20th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 19th through Monday Morning 8:00AM (Start of Classes) March 22nd. Please make sure that you plan your schedules accordingly. BURTON HALL ENTRANCE Starting Friday at 5:00PM, March 12, the Burton Hall Entrance will be closed through the end of Summer for the construction of the new wheelchair lift and ADA Accessibility. ROOM BY ROOM SCHEDULE (Dated 3/5/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 3/5/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next 4 weeks. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
February 26, 2010: The abatement process for the project is moving along very well. As you might have noticed the north side of the 3rd and 4th floor hallways of Sabin Reed has been abated and all levels of the North Stair have been abated as of last night. As a reminder the following rooms WILL NOT have access to them over this weekend beginning tonight at 5:00PM Friday, February 26 through Monday Morning 8:00AM (Start of Classes) February 28:400, 407, 407A, 408, 410, 411, 413, 414, 415, 416, 435, 436, 437, 437A, 438, 439, 440, 441, 442, 443, 444, 445, 446 & 447. Again, this section of corridor and rooms might also be closed off the following weekend (March 5 starting at 5:00PM March 8 at 8:00AM) as it is not known how easily or hard the floor tiles can be removed. Once the first weekend work of each area has concluded will we know if the following weekend will be required to complete the abatement. You will be updated early in the week as to the status of the accessibility to the rooms for the following weekend. The project contractors will also begin to core through some occupied spaces beginning next week. I have discussed these rooms with those that will be affected by this upcoming operation. As well as coring they will begin to layout and frame some of the electrical/data closets for this project. NON ACCESSIBLE 4TH FLOOR ROOMS DURING WEEKEND OF MARCH 6th & Possibly WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 4th Floor Sabin Reed Corridor (401, 402, 402A, 403, 404, 405, 406, 406A, 406B, 449, 450, 451, 452, 453, 454, 455, 455A, 456 & 457) will not be accessible next weekend March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 5 through Monday Morning 8:00AM (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 13th & Possibly WEEKEND OF MARCH 20th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 306, 307, 308, 309, 342, 342A & 342B) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 12th through Monday Morning 8:00AM (Start of Classes) March 15th. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 20th & Possibly WEEKEND OF MARCH 27th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 301, 302, 303, 303A, 304, 304A, 304B, 305, 343, 344, 345, 346, 347, 348, 349, 350, 351, 352) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 19th through Monday Morning 8:00AM (Start of Classes) March 22nd. Please make sure that you plan your schedules accordingly.
ROOM BY ROOM SCHEDULE (Dated 2/26/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 2/26/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next month. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
February 19, 2010: The abatement process for this project kicked off on Wednesday 2/17/10 and it was determined to minimize potential disruption on the 3rd floor, the abatement work has moved to off hours beginning at 5:00PM. Please keep in mind that we monitoring the air outside of the abatement areas to ensure occupant safety. Currently the 3rd Floor North side hallway has been encapsulated and floor tiles have been removed and grinding activities will continue through the end of this weekend. The abatement contractor is making preparations to encapsulate the 4th Floor North side hallway and abatement of this section of hallway is scheduled to begin early next week. As previously indicated, the following rooms WILL NOT have access to them over next weekend beginning 5:00PM Friday, February 26 through Monday Morning 8:00AM (Start of Classes) February 28. Please make sure that you plan your schedules accordingly:400, 407, 407A, 408, 410, 411, 413, 414, 415, 416, 435, 436, 437, 437A, 438, 439, 440, 441, 442, 443, 444, 445, 446 & 447. Again, this section of corridor and rooms might also be closed off the following weekend (March 5 starting at 5:00PM March 8 at 8:00AM) as it is not known how easily or hard the floor tiles can be removed. Once the first weekend work of each area has concluded will we know if the following weekend will be required to complete the abatement. You will be updated early in the week as to the status of the accessibility to the rooms for the following weekend. NON ACCESSIBLE 4TH FLOOR ROOMS DURING WEEKEND OF MARCH 6th & Possibly WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 4th Floor Sabin Reed Corridor (401, 402, 402A, 403, 404, 405, 406, 406A, 406B, 449, 450, 451, 452, 453, 454, 455, 455A, 456 & 457) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 5 through Monday Morning 8:00AM (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 3rd FLOOR ROOMS DURING WEEKEND OF MARCH 6th & Possibly WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (300, 306, 307, 308, 309, 342, 342A & 342B) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 5 through Monday Morning 8:00AM (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly.
ROOM BY ROOM SCHEDULE (Dated 2/19/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed. 1 MONTH LOOK AHEAD SCHEDULE (Dated 2/19/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next month. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
February 12, 2010: Please be advised that construction for this project will begin on Tuesday February 16, 2010.As you may have seen on the 4th and 3rd Floor North Side of Sabin Reed, the contractor has begun to install some partitions in preparation for the abatement process that will begin on Tuesday, February 16th. On the 16th, the abatement contractor will install the full encapsulation on the 3rd Floor North Side and on Wednesday 2/17/10 they will begin the actual removal of ACM (Asbestos Containing Material) floor tile. This activity will create noise as they will need to grind down the adhesives that hold down the tiles. Once they have completed the 3rd Floor abatement, they will move up to the 4th floor and work from the North to the South side of the building. NORTH ELEVATOR The North Elevator will have no access to the 3rd and 4th Floor beginning Tuesday, February 16th. Please use either the South Elevator or the Center Elevator NORTH STAIR Starting Friday, February 19th, the North Stair will be shutdown until all work associated with the I/C/DM portion of the project is completed. ABATEMENT OF CORRIDOR FLOORS Due to the uncertainty of how much of the ACM Floor tile can be removed from the corridor floor, the contractor has pushed out the weekend work for the effected "Occupied" spaces to include 2 concurrent weekends. Not until the removal of the floor tile on each floor and within each section as indicated on the schedule will they know how easily or hard the tile can be removed which ultimately will effect the areas that can be abated during the weekend. Once the first weekend work of each area has concluded will we know if the following weekend will be required to complete the abatement. You will be updated early in the week as to the status of the accessibility to the rooms for the following weekend. NON ACCESSIBLE 4TH FLOOR ROOMS DURING WEEKEND OF FEBRUARY 27th & Possibly WEEKEND OF MARCH 6th 4th Floor Sabin Reed Corridor (400, 407, 407A, 408, 410, 411, 413, 414, 415, 416, 435, 436, 437, 437A, 438, 439, 440, 441, 442, 443, 444, 445, 446 & 447) will not be accessible during the weekend of February 27th and possibly the weekend of March 6th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, February 26 through Monday Morning 8:00AM (Start of Classes) February 28. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 4TH FLOOR ROOMS DURING WEEKEND OF MARCH 6th & Possibly WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 4th Floor Sabin Reed Corridor (401, 402, 402A, 403, 404, 405, 406, 406A, 406B, 449, 450, 451, 452, 453, 454, 455, 455A, 456 & 457) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 5 through Monday Morning 8:00AM (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly. NON ACCESSIBLE 3RD FLOOR ROOMS DURING WEEKEND OF MARCH 6th & Possibly WEEKEND OF MARCH 13th As also indicated on the Room by Room schedule, rooms listed within the 3rd Floor Sabin Reed Corridor (301, 302, 303, 303A, 304, 304A, 304B, 304C,305, 306, 307, 308, 309, 342, 343, 344, 345, 346, 347, 348, 349, 350, 351 and 352) will not be accessible during the weekend of March 6th and possibly March 13th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning 5:00PM Friday, March 5 through Monday Morning 8:00AM (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly.
ROOM BY ROOM SCHEDULE (Dated 2/12/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed.
1 MONTH LOOK AHEAD SCHEDULE (Dated 2/12/10) Below you will find a snapshot of the upcoming construction activities scheduled for the next month. Please refer back to the Room by Room schedule for dates that your spaces will not be accessible during the weekends.
February 5, 2010: Please be advised that construction for this project will begin on Tuesday February 16, 2010.As this project moves forward, you will be updated on scheduled activities and the locations of these activities. Please be sure that you review the Room by Room Schedule as they are distributed to ensure that you are aware of the "Restricted Access" dates as they relate to the abatement of the floors within the corridors. Currently the schedule indicates that rooms listed within the 4th Floor Sabin Reed Corridor (400, 407, 407A, 408, 410, 411, 413, 41, 437, 437A, 438, 439, 440, 441, 442, 443, 444, 445, 446 & 447) will not be accessible during the weekend of February 27th as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning the end of day Friday February 26 through Monday Morning (Start of Classes) February 28. Please make sure that you plan your schedules accordingly. As also indicated on the Room by Room schedule, rooms listed within the 4th Floor Sabin Reed Corridor (401, 402, 402A, 403, 404, 405, 406A, 406B, 406C, 448,448A, 448B, 449, 450, 451, 452, 453, 454, 455, 455A, 456 & 457) will not be accessible during the weekend of March 6rh as the abatement within this section of the corridor will be completed. No access to these rooms will be allowed beginning the end of day Friday March 5 through Monday Morning (Start of Classes) March 7th. Please make sure that you plan your schedules accordingly. You should also be advised that the North Stair will not be accessible until the end of Phase One. Please use either the South Stair or Central Stair.
ROOM BY ROOM SCHEDULE (Dated 2/5/10)- 4th & 3rd Floor Sabin Reed Below you will find a Room by Room Schedule for the 4th and 3rd Floor of Sabin Reed.
Go back to Science Center Director's Office - Main Page
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||